Before renovation

Production efficiency requirements

  • Automobile processing enterprises

  • Sawing bar material

  • 45#steel

  • 3000/piece/day

  • Length 300mm

  • Accuracy requirements30

Current equipment

  • 20 band sawing machines

  • 6 operators

  • 3000 square meters of venue

Costing

  • Salary: 36000 per month

  • Saw blade: 20000/month

  • Oil product: 8000/month

  • Electricity fee: 8000 per month

  • Equipment depreciation: 8000/month

    (with a cost of 50000 yuan)

Comprehensive cost

  • 71000/month

After transformation

Production efficiency requirements

  • Automobile processing enterprises

  • Sawing bar material

  • 45#steel

  • 3000/piece/day

  • Length 300mm

  • Accuracy requirement 30

Current equipment

  • 1 intelligent sawing production line

  • 1 operator

  • 2000 square meters of venue

Costing

  • Salary: 6000 per month

  • Saw blade: 2000/month

  • Oil product: 5000/month

  • Electricity fee: 5000/month

  • Equipment depreciation: 2700/month

    (15 year depreciation)

Comprehensive cost

  • 40500/month

Cost savings of 360000 yuan per year after renovation